EARTH & SPACE / PROGRAM ATLAS

THE ZENIT PROGRAM / 27 NOVEMBER 2026

KETS power.
Heat accounted for.

Two completed conditional studies of the Gen 2 per-wing target.

The JavaScript has already been run: 14 checks passed for the power account and 17 for the operating envelope. The calculations expose the source and cooling requirements behind the 99.91 MW net target.

99.91MW net target
273.863MW particle diversion required
82.209MW usable KCS rejection required
31Internal model checks passed

KETS CALCULATIONS

Run the KETS calculations

The studies run on the server using their saved assumptions. Results appear below. These are conditional numerical studies; physical qualification remains open.

Preparing the calculations…

Power and cooling

Per-wing account using the saved conversion and auxiliary assumptions.

Waiting to calculate

Operating envelope and thermal response

Transient rows use a five-second heat-release assumption; the authored cooling faults begin at 60 seconds.

Waiting to calculate

COMPLETED NUMERICAL STUDY / R1

The 99.91 MW net target needs a larger account.

Under the inherited assumptions, the net target requires 273.863 MW of particle diversion and 82.209 MW of dedicated KCS rejection per wing. Two identical wings sum to 199.82 MW net gain and 164.418 MW KCS duty; one wing cannot spend the other wing’s reserve.

Conditional power account: one wing, zero replacement heating
Per-wing quantityMW
Diverted particle power273.863
Converter electricity before delivery191.704
Delivered converter electricity182.119
Displaced thermal electricity82.159
Additional auxiliary demand0.050
Net electrical gain target99.910
Dedicated KCS heat rejection82.209
Change in main rejected heat-182.119

The account uses 70% direct conversion, 95% delivery, 30% displaced thermal-electric output, 80% replacement-heater efficiency, and a favorable 50 kW fixed auxiliary load per wing. The nominal row assumes zero replacement heating. The bus balance is delivered converter output minus displaced thermal electricity, heater electricity and extra auxiliaries.

The KCS duty is not an equal increase in total vessel waste heat. In this fixed-reactor comparison, main rejected heat falls as energy leaves the earlier thermal path. The combined rejected-heat change balances the added bus electricity. Reactor/plasma response and the full plant remain outside this incremental account.

Interpretation and sensitivity

If 99.91 MW meant delivered converter electricity rather than net gain, the same assumptions would yield only 54.788 MW net. This check does not change the recorded net target.

The grid evaluates 6,561 authored parameter combinations: 3,231 have a positive algebraic root and 3,330 do not. They are sensitivity cases, not probabilities or accepted configurations. At 30% replacement heating, the nominal efficiencies give no positive diversion solution for the target.

The inherited cooling path does not support this pulse.

R1 pulse screen: immediate converter heat release, 180 seconds including ramps
Usable KCS MWRequired external buffer MJ100 MJ reached after first diversion s
1.55012,875.9717.343
40.0006,342.93816.703
80.000310.43465.003
82.2090.000Not reached in this model
90.0000.000Not reached in this model

With 1.55 MW of usable rejection, the 100 MJ allocation fills after about 7.343 seconds. Required buffer means the unbounded diagnostic peak; heat above the capped allocation is explicitly unaccommodated. A zero peak at a higher declared rejection rate does not qualify a physical radiator.

Electrical runoff is a separate account.

Separate electrical converter-runoff screen; one-second linear rundown
Isolation delay sGross converter feed energy MJUsing net gain as feed MJOmitted energy MJ
0.25136.58974.93361.657
2455.297249.775205.522

The gross converter feed exceeds the net increment because displaced generation is subtracted only in the net comparison. The electrical dump/buffer screen does not model whole-wing shutdown, rotor or magnetic energy, primary generation, or the final heat destination. Its historical 1 GJ electrical buffer is separate from the 100 MJ thermal allocation.

The separate 87.5 MW turbine output is not credited to this net ledger. Converter heat alone is below that output even at ideal conversion; another declared heat input would require its own account.

COMPLETED NUMERICAL STUDY / R2

Steady derating does not remove stored heat.

The reference takes the smallest diversion allowed by the net target, declared available particle surplus and usable KCS rejection. Data acceptance, protected-load acceptance and physical permission remain separate requirements. Docking and atmospheric operation request bypass.

R2 source and cooling envelope; an unassessed value is not a measured zero
Declared condition per wingConditional net gain MWInterpretation
Nominal assumed inputs99.910Calculated estimate under declared bounds
80 MW usable KCS97.222Calculated estimate under declared bounds
40 MW usable KCS48.556Calculated estimate under declared bounds
200 MW declared particle surplus72.950Calculated estimate under declared bounds
10 percent heating replacement65.677Calculated estimate under declared bounds
30 percent heating replacement0.000Bypass requested; no gain credited
One percent extra auxiliary fraction94.035Calculated estimate under declared bounds
Missing particle observationUnassessedNo operating estimate
Unaccepted observationsUnassessedNo operating estimate
Docking0.000Bypass requested; no gain credited
Atmospheric mode0.000Bypass requested; no gain credited
Protected loads unacceptedUnassessedNo operating estimate

Zero in a bypass row means no optional gain is credited by the request. It does not mean existing heat instantly disappears. Missing or unaccepted observations remain unassessed.

A cooling change can exceed the buffer after power is reduced.

R2 transient comparison: event at 60 seconds, 0.25-second delay and one-second diversion rundown
Cooling eventHeat-release time sRequired external buffer MJPeak unrated converter heat MJ
Cooling decreases to 40 MW031.6570.000
Cooling lost for 30 seconds, diversion remains isolated063.1190.000
Cooling decreases to 40 MW5242.667410.762
Cooling lost for 30 seconds, diversion remains isolated5472.695410.762
Cooling decreases to 40 MW15616.7391,185.974
Cooling lost for 30 seconds, diversion remains isolated151,079.2411,185.924

At five seconds of heat-release lag, the 40 MW cooling case needs 242.667 MJ externally, exceeding the inherited 100 MJ allocation. For this authored event alone, pre-event derating to about 69.720 MW net fits the declared allocation. For a 30-second complete loss with diversion isolated, the analogous pre-event value is 20.846 MW net. These are conditional fault-case limits, not new vessel ratings.

The converter inventory is heat awaiting release and has no accepted physical capacity or temperature range. The external buffer diagnostic can exceed 100 MJ to expose a deficit; a physical 100 MJ buffer does not gain that capacity. Circulation continues while heat remains. Restoring cooling does not automatically restart isolated diversion.

Evidence needed before accepting a configuration

Measure available particle surplus, heater and auxiliary demand, converter thermal mass and temperature limits, heat-release and isolation response, time-dependent usable rejection and buffer enthalpy. Complete the main thermal return, protected-service and independent protection accounts. AXIOM retains final physical permission and ZSA owns independent acceptance. These models calculate no new thrust, cruise or braking performance.

ALREADY EXECUTED / REPRODUCIBLE

Inspect the results and model checks.

Expand each study below to read the checks it passed.

Gen 2 KETS power and cooling

14 internal checks passed.

Inspect the passed model checks
  • Legacy per-branch net and KCS values reproduced
  • Every positive target solution reproduces the requested net gain
  • Converter input closes to electricity plus converter heat
  • Net electrical change and total rejected-heat change balance
  • Gross bus output is distinct from net gain
  • Full heating replacement cannot meet the nominal net target at the nominal efficiencies
  • Legacy pulse does not fill its matched nominal KCS buffer
  • All pulse energy stays in rejection, declared storage or explicit unaccommodated heat
  • Inherited KCS capacity inhibits the new target in the reference screen
  • A sufficient declared rejection path fits this lumped heat model
  • Wing A cooling loss does not spend Wing B capacity
  • Time-step refinement leaves the early buffer threshold stable
  • Net-gain proxy understates isolated gross converter runoff
  • Invalid negative input is rejected

Gen 2 KETS operating envelope and thermal response

17 internal checks passed.

Inspect the passed model checks
  • Nominal envelope reproduces the prior 99.91 MW reference
  • Cooling-limited derating respects both declared bounds
  • 80 MW cooling gives 97.2225 MW net in the inherited model
  • A 200 MW particle limit gives 72.95 MW net
  • Heating replacement removes the benefit when the net coefficient is nonpositive
  • Extra auxiliaries cannot increase the accepted net gain
  • Missing or unaccepted observations remain unassessed
  • Docking and atmospheric modes stay in bypass
  • Protected-load acceptance is a separate reference gate
  • Transition heat balances include both converter and external buffer inventories
  • All modeled state inventories and diversion stay nonnegative
  • Thermal release lag can exceed the external buffer even after steady derating
  • Restored cooling does not automatically restart isolated diversion
  • Pre-event derating fits the declared partial-cooling case
  • Pre-event derating fits the declared temporary-loss case
  • The zero-lag extension reproduces the prior unbounded pulse inventory
  • Time-step refinement keeps the transient buffer requirement stable

Research context

The studies extend the project’s recorded KETS energy comparison, pulse trial and MAGTRANS protection demonstrator. Earlier pump, buffer and response values retain their reference scope; the electrical isolation timings are hypothetical when applied to particle diversion. No fleet-wide hardware capacity follows from this per-wing calculation.

The current Zorak study follows one command through cooldown and accounts for both grid-powered pumps. The earlier 50-minute fleet replay uses ten repetitions to estimate the thrust each major vessel would need to match the flagship.